How many days do subcontractors have to provide a "notice of furnishing" after the first delivery of goods or services?

Prepare for the Michigan Builders License Exam. Study with flashcards and multiple choice questions, each question having hints and explanations. Get ready for your exam!

Subcontractors must provide a "notice of furnishing" within 20 days after the first delivery of goods or services. This notice is a critical step in ensuring that they preserve their right to file a construction lien if necessary. By adhering to this timeline, subcontractors can formally notify the property owner and the contractor of their involvement in the project, which helps protect their legal rights regarding payment.

Providing this notice within the specified timeframe facilitates clear communication among all parties involved and helps to prevent potential disputes over payment. Understanding this requirement is essential for subcontractors working in Michigan's construction industry, as it directly impacts their ability to enforce their rights should payment issues arise.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy