What is the purpose of temporary erosion control measures during construction?

Prepare for the Michigan Builders License Exam. Study with flashcards and multiple choice questions, each question having hints and explanations. Get ready for your exam!

Temporary erosion control measures during construction are specifically designed to reduce immediate sediment runoff. During construction activities, there is a significant risk of soil erosion due to disruptions in the soil surface. Rainfall or surface runoff can mobilize loose soil particles, leading to sediment being washed away into nearby water bodies, which can cause pollution and environmental degradation.

By implementing temporary measures such as silt fences, straw bales, or temporary seedings, construction sites can effectively minimize the transport of sediment during the critical phases of soil disturbance. These controls are crucial for protecting water quality and complying with environmental regulations, as they help contain sediment on-site until more permanent measures can be established.

The other choices do not fit the specific role of temporary erosion control measures during construction. While stabilizing soil permanently is important, that falls outside the scope and timeframe of temporary measures. Facilitating easier construction and enhancing aesthetic appearance are also not primary purposes; rather, they may be considered secondary benefits but do not address the critical issue of sediment management during active construction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy